When a process drifts, contain everything made since the last good check, then rule out the measurement system with a Gage R&R. Plot the characteristic on a control chart to see whether the shift is real, use Cp and Cpk to tell a centering problem from a spread problem, find what changed, update the Control Plan so the next drift is caught before parts go out of tolerance, and prove the fix held.
Start with
Contain what was made since the last good check, then rule out the gage before you blame the process.
Drift has a cause, and it usually shows up in the data before it shows up as scrap. Work in this order so you are not adjusting a good process to chase gage noise. The free field book One Drifting Shaft. The Process Trail. follows one made-up drift through all eight steps, one chapter per step.
The path, in order
Spot the drift
Read the check sheet for direction, not pass or fail. Readings rising several checks in a row, or past halfway to a limit, mean stop and call the lead while every part is still good. Put that call rule on the sheet so nobody has to argue for it.
Containment
Everything made since the last good check is suspect, not just since the first bad reading. Count what the machine made in that window, find every piece until the count matches, red tag it and send a quality alert downstream. Do not sort until the gage is trusted.
Chapter 2: Contain It. Guide: How to quarantine and red tag material. Free tool: Containment checklist builder.
Gage R&R
If the gage varies, the drift may be measurement noise. Confirm repeatability and reproducibility before chasing the process. Check calibration status and the gage resolution while you are there.
Chapter 3: Rule Out the Gage. Guide: Gage R&R explained. Guide: How to track gage calibration
Control chart
Plot the data in time order, with limits set from a stretch you trust, not from the print. Look for shifts, trends and points outside the limits that signal a special cause. Write down when the change began. The next steps need that time.
Chapter 4: Read the Chart. Guide: SPC control charts for beginners
Capability
Compare Cp and Cpk. If Cp holds and Cpk falls, the average moved, so look for what shifted it. If both fall, something is adding variation. A quick look at recent pieces tells you where to look. Use a full study when you need a number to show a customer.
Root cause
Match the timing of the change to what changed: tool wear, material lot, setup, operator or environment. Check each against records, not memory. A fishbone keeps the team from settling on tool wear just because it is the usual suspect.
Chapter 6: Find What Changed. Guides: How to make a fishbone diagram and How to do a 5 Why. Free tool: 5 Why helper.
Control Plan
Add or tighten the control and its reaction plan so the next drift is caught early, while parts are still good. Name the trigger, who stops the machine, and what has to be true to restart.
Chapter 7: Lock It In. Guide: How to write a control plan. Free download: Control Plan blank.
Prove it held
Set the proof before you look: a fresh capability run and a window with no chart signals. Close the corrective action only when the window is clean. Then add a layered process audit question so someone checks the fix stays in place.
Chapter 8: Prove It Held. Guides: How to run an effectiveness check and How to run a layered process audit
Use these next
- One Drifting Shaft. The Process Trail.: the whole path as a free field book
- The Monday Board: eight drift checks on one printable page
- Gage R&R explained: how to run a study and read the numbers
- SPC control charts for beginners: which chart, and what the signals mean
- Cpk vs Ppk: what they mean and how to calculate them in Excel
- Control Plan vs PFMEA
- Field Book: write a reaction plan that works
- Free tool: 5 Why helper
- On Etsy: the Process Trail Bundle, all 13 tools on this path in one set, or the shorter SPC & Process Capability Bundle. All measurement workbooks