New part launch: build the PFMEA before the Control Plan

A new part or process is launching and the PPAP is due.

For a new part launch, set it up on day one, write the PFMEA before the control plan and build the plan from it, train the station, prove your gages with a Gage R&R, make the first article from production parts, run at rate to measure capability, and assemble the PPAP submission at the level your customer requires.

Start with

Confirm the PPAP level and customer requirements on day one, then start the PFMEA before the Control Plan.

Most launch trouble starts when the paperwork is filled in after the process is built. Work in this order so each record feeds the next one, and the PPAP package is mostly assembled by the time it is due. The free field book One New Part. The Launch Trail. follows one made-up part through all eight steps, one chapter per step.

The path, in order

  1. Set up the launch

    Read the drawing and the customer requirements end to end, find the special characteristics and confirm the PPAP submission level on day one. Draw the process flow and write the PPAP plan with an owner and a week for every element, working backward from the due date. Aim to send it two days early.

  2. PFMEA

    Walk the process flow step by step. For each step, list how it can fail, the effect and the cause. Rate the risks with Action Priority and decide actions while the process can still change. Get the people who will run the process in the room, not just engineering.

  3. Control Plan

    For each product and process characteristic, set the specification, measurement method, sample size and frequency, control method and reaction plan, drawing on the PFMEA. Every high risk in the PFMEA should land on a row here. If one does not, that is a gap you will find at the customer.

  4. Work instruction and training

    The plan only works if the operator at the station can follow it. Write the work instruction for the station, release it at a revision, and watch each operator find a planted bad part before you sign them off. A signature shows someone sat through a briefing, not that they can do the job.

  5. Gage R&R

    Confirm every gage used on key characteristics can tell good parts from bad before you trust its readings. If a fixture fails, fix it and run the study again. Run it before the capability study, or the study measures your gage as much as your process.

  6. First article

    Measure parts from the production process against every characteristic on the drawing and record the results. Number each characteristic on the drawing, record one result for each, and note the gage used, so anyone can trace a number back to the print.

  7. Run at rate

    A first article shows the tool can make good parts. A significant production run, at production speed with production tooling, people and gages, shows the process can keep making them. Measure capability on the whole run. Do not stop when the numbers look good: resin changes, shift changes and tool warm-up show up late. The customer sets the run size and the minimum index.

  8. PPAP

    Assemble the elements your customer requires at the submission level they specify, with the Part Submission Warrant. Make every record agree with every other, and check every entry on the warrant before it is signed. If it comes back rejected, turn each reason into one action with an owner and a date.