OEE calculator

One shift in, availability, performance, quality and OEE out, with the minutes lost to each.

Enter the shift length, planned stops, unplanned downtime, the ideal cycle time and the part counts for one shift on one machine. The calculator works out availability, performance and quality, multiplies them into OEE, and shows where the planned time went in minutes, so you can see which loss to attack first.

Nothing you enter leaves your browser. Clearing or closing the page removes it.

The formulas it uses

  • Planned production time = shift length minus planned stops.
  • Run time = planned production time minus unplanned downtime.
  • Availability = run time divided by planned production time.
  • Performance = ideal cycle time times total parts, divided by run time.
  • Quality = good parts divided by total parts.
  • OEE = availability times performance times quality. It works out the same as good parts times ideal cycle time, divided by planned production time.

Worked example

The example button loads a made-up shift: 480 minutes, 40 minutes of planned stops, 52 minutes of unplanned downtime, a 30 second ideal cycle, 640 parts made and 18 rejected. Availability is 388 of 440 minutes, 88.2 percent. Performance is 320 ideal minutes of work in 388 minutes of run time, 82.5 percent. Quality is 622 good of 640, 97.2 percent. OEE is 70.7 percent. Of the 440 planned minutes, 311 went to good parts at the ideal rate, 52 to downtime, 68 to slow cycles and small stops, and 9 to the rejected parts. The full method is in how to calculate OEE.

This is a calculator for one machine and one shift. It cannot tell if your inputs are right. If performance comes out over 100 percent, the ideal cycle time is too slow or the part count is off.