8D report example: a complete 8D, step by step

A filled-in 8D for one made-up complaint, from the team to the closing check.

This is a complete 8D report for one made-up complaint: weld nuts that spun loose at the customer. It shows what a good entry looks like in each of the eight disciplines, with containment counted at every location, three root causes proven by a trial, one action per cause, and an effectiveness check with numbers before it closes.

The case: bracket 4410-B is a laser cut, press brake formed steel bracket with an M8 nut projection welded on. The customer bolts it into an assembly. Lot 2610-14, 1,200 pieces, shipped and then came back as a complaint: nuts spinning loose when the bolt was torqued.

D1: Team

RoleWhy they are on it
Quality engineer (lead)Owns the 8D, the customer contact and the evidence.
Weld cell leadRuns the projection welder every day and knows the setup.
Maintenance technicianOwns the electrodes, tip dressing and the weld controller.
Production supervisorOwns the schedule, staffing and the containment sort.
Customer quality engineerConfirms the problem statement and the clean break at their end.

D2: Problem statement

Customer reported 37 brackets, part 4410-B, from lot 2610-14 (1,200 pieces), where the M8 weld nut spun when the bolt was torqued on their assembly line. Found at the customer on day 1 of use. Returned parts pushed out at 1.1 to 1.6 kN against a 4.0 kN minimum. No spun nuts reported on earlier lots.

Read it back: someone who was not there can check every number in it. See How to write a problem statement.

D3: Containment

Every location that could hold suspect brackets was checked within 24 hours. Each nut got a proof torque check, which does not damage a good weld.

LocationQuantity checkedFailedAction
At the customer1,163 (1,200 less the 37 found)9Sorted on site, failed parts returned
In transit400 (lot 2610-15)3Intercepted and sorted on arrival
Finished goods8006Sorted, failed parts red tagged
Work in process3002Sorted, failed parts red tagged
Total2,66320, plus the 37 found

Clean break: lot 2611-02, the first lot welded after the tip dress interlock went in and checked 100 percent. Certified boxes carry a green dot on the label until the effectiveness check closes.

D4: Root cause

Three legs, each with its own chain of whys. The full chain is on the 5 Why example.

LegRoot causeEvidence
Occurrence: why the welds were weakElectrode tips were dressed once per shift by the clock. After the run rate went up, tips wore past their limit before the next dress.Weld counter showed about 1,100 welds per shift, up from about 600. Trial below.
Detection: why we did not catch itThe push-out test was done on the first piece of the shift, right after a fresh dress, so it only ever tested the best case.Control Plan and test records: one test per shift, all at shift start.
System: why the system allowed itThe run rate change was treated as a scheduling decision, not a process change, so nobody reviewed the PFMEA or the dress interval.Change request list covers tooling, material and method. Volume is not on it.

Verified by turning it on and off. 40 nuts welded with tips at the end of the old interval: 9 failed push-out. 40 nuts welded after a fresh dress: 0 failed.

D5: Permanent corrective actions

LegActionOwner
OccurrenceTip dress by weld count, every 400 welds, with a controller interlock that stops the welder at the count.Maintenance
OccurrenceWeld current monitoring on every weld, with a fault stop and reject when current falls outside the window.Maintenance
DetectionPush-out test on the last part before each tip dress, the worst case, as well as the first piece.Quality
SystemRun rate and shift pattern changes added to the change request trigger list, with a PFMEA review.Quality manager

D6: Implement and validate

Interlock and current monitoring installed and tested in week 1. Push-out test frequency changed in the Control Plan and work instruction the same week. Validation over the next three weeks: 126 push-out tests on end-of-interval parts, all above 4.0 kN, and 0 current faults that reached a part.

D7: Prevent recurrence

  • PFMEA updated. The weld row was re-rated and now has the new controls. See the PFMEA example.
  • Control Plan updated. New rows for weld current, tip dress count and the end-of-interval push-out test. See the Control Plan example.
  • Work instruction updated. Tip dress steps and the push-out sampling, with photos of a good and a bad weld.
  • Read across. The same interlock and test change applied to the second projection welder, which had the same time-based dress.
  • LPA question added. "Is the tip dress counter active and below 400?" checked at every layer.

D8: Close and recognize the team

Closed only after the effectiveness check: six consecutive customer lots with no spun nuts and no push-out failures in our own data over 90 days. Team thanked at the shift meeting, with the weld cell lead credited for spotting the run rate change.

Everything on this page is made up for the example: the part, the numbers, the customer and the team. Use your own forms, rating scales and customer requirements.